KFS approves pipeline installation inside Karura Forest
National
By
Esther Nyambura
| Mar 06, 2026
The Kenya Forest Service has approved the installation of a section of water transmission pipeline within Karura Forest.
The approval allows Athi Water Works Development Agency to access the forest to construct part of the Gigiri–Karura–Outer Ring Road transmission pipeline, a project they say aims at boosting water supply to eastern parts of Nairobi.
The pipeline, which is part of an 8.4-kilometre bulk water transmission system, is to be installed underground along an existing cycle track corridor between Whispers Avenue and Kiambu Road and is said to be designed to increase water conveyance capacity within the city.
"The DN1400 transmission pipeline will run from Gigiri Reservoir to Karura Reservoir and onward to Outer Ring Road. A 3-kilometre portion of the Gigiri–Karura section will be installed underground within an existing cycle track corridor inside Karura Forest, from Whispers Avenue to Kiambu Road (KFS Gate C."
Once completed, Athi Water Works says the project is expected to deliver an additional 211 million litres of water per day.
READ MORE
China woos Kenyan producers with '800-million opportunity' as zero-tariff deal takes effect
Co-op bank shares set for further gains on strong profit growth, lower rates
Kenya slashes dollar debt to record low as Chinese yuan gains ground
Government plans stricter laws to clean up tea sector
Tourism earnings hit record Sh500 billion as arrivals near 8m
Kakamega youth, women eye avocado export cash after skills training
Portable kitchen: Designer taps into space-saving trend
Kenya urged to pilot AI regulatory Sandbox in bid to lead Africa's digital future
MPs pledge site visist as KTDA gives progress on hydro power project
According to the authority, the works will involve limited vegetation clearance within the designated corridor, with authorities noting that affected trees will be replaced in line with forest management guidelines.
"Installation works within the forest are scheduled for completion within four months (120 days), after which affected areas will be reinstated and restored in accordance with approved environmental management plans."
The construction works within the forest are expected to take approximately four months, after which the site will be restored in line with environmental management plans.