How hurdles are threatening Kenya's pace in sports infrastructure
Sports
By
Stephen Rutto
| Nov 18, 2026
As Kenya basks in glorious moments and achievements produced in recent outings, including the Dakar Youth Olympic Games, stadia, which are a critical pillar in their career growth, remain unachieved, although progress has been made.
From athletics to rugby and from volleyball to swimming and tennis, Kenyan talents have lit up global arenas.
Jaw-dropping performances such as the phenomenal sub-two-hour marathon world record delivered by Sebastian Sawe in April and impressive results achieved by athletics stars at the World Cross Country Championships in Tallahassee in January cement Kenya’s dominance on the global stage.
READ MORE
What to expect as Ruto delivers fourth State of the Nation Address
Why the '666' exam dispute did not have to end with police intervention
Education chiefs dismisses KCSE malpractice claims
Ogamba: KCSE supervisor assault not exam-related
When candidates declare war on examiners, nation's future is bleak
Stage set for Duracoat Golf Masters grand finale
Kenyan future stars leave an indelible mark in Dakar
Rono braves Oregon storm to bag Youth Olympic gold
Kenyan teens brave Dakar heat to storm Youth Olympics podium
Moving target: Why Kenya's dream of industrialising keeps being deferred
But key promises have been made on sports flagship projects such as Raila Odinga International Stadium at the Talanta Sports City in Nairobi.
The 60,000-capacity ultramodern sports facility is set for an opening match between German giants FC Bayern Munich and Dutch greats AFC Ajax on January 5 when it is expected to have achieved at least 99 per cent completion.
However, save for Nyayo National Stadium and Ulinzi Sports Complex both in Nairobi, several other stadia across the country remain under construction and are unable to host training sessions and competitions in their current state.
Moi Sports Centre Kasarani is undergoing an upgrade as one of the venues, alongside Raila Odinga Stadium, for the 2027 Africa Cup of Nations (Afcon).
In 2025, President William Ruto outlined an ambitious plan to transform Kenya’s sporting sector through infrastructure development, talent identification and commercialisation.
The government pledged to establish at least 30 sports academies and construct 22 additional stadia in a drive to make sports a driver of job creation, investment and economic growth.
The upgrade of these projects has been marred by a slow pace of construction, with nearly all the sporting facility projects running behind schedule.
For instance, Raila Odinga Stadium was scheduled for completion in December 2025, but the project faced delays before reaching approximately 94 per cent completion by last month.
The race to host Afcon in 2027 and the World Athletics Championships in 2029 are the latest factors that are helping to push the pace in Kenya’s race for world-class sports infrastructure.
Kakamega’s Bukhungu Stadium, which is still undergoing upgrades, is set to be a football epicentre upon completion.
Kipchoge Keino Stadium, which hosted Mashujaa Day, is among flagship projects that had stalled, but has been revived as Kenya gets ready to co-host the AFCON alongside Uganda and Tanzania next year.
Mid last month, President Ruto told World Athletics President Sebastian Coe in Eldoret that Kasarani would be ready to host the 2029 World Athletics Championships.
“The Moi International Sports Centre, Kasarani, the venue of the championships, is undergoing major upgrades ahead of 2027 Afcon and will be further improved for the athletics event,” Ruto said during a meeting with the global body’s head in Eldoret.
Despite construction of modern stadia across the country being in progress, the ever-rising costs of upgrades remain a major concern.
In July, the Auditor-General flagged an unsupported Sh10.848 billion price variation between the Sh35 billion approved by the National Treasury and the Sh45.848 billion contract value for Raila Odinga Stadium.
“There were other factors that had not been factored and these are mostly the taxes. The contractor is expected to pay taxes including VAT, withholding tax, and of course when you are importing, you are required to pay the freight charges and clearing charges,” Sports Principal Secretary Elijah Mwangi told parliament in August.
In the last three years, Kenya has allocated Sh78 billion for sports infrastructure.
Kipchoge Keino Stadium, whose cost rose from Sh300 million to Sh3.5 billion, is set for completion on December 31, according to the implementing agency – Sports Kenya.
Sports Kenya Director General Timothy Kilimo said an event that meets World Athletics standards will be staged at the 15,000-seater Kipchoge Keino Stadium in March next year after completion of the full upgrade.
“We want to assure sports talents that by next year, there will be a new stadium with a new tartan and there will be a pitch that meets CAF and FIFA standards and it will be one of the best venues outside Nairobi.”
“This is the fourth largest stadium in Kenya. The other three are in Nairobi,” he said during an inspection of the facility.
He added: “There will also be a football match to test the standards ahead of AFCON. Works are also progressing at Kipchoge Stadium in Kapsabet in Nandi County and at Kamariny in Elgeyo Marakwet. President William Ruto will inspect the sporting facilities.”
Kenya’s race for modern stadia has also been rocked by contractual controversies, causing delays in a number of projects.
Masinde Muliro Kanduyi Stadium in Bungoma and Kamariny faced contract cancellation in 2026 and 2020, respectively, following delays.
In June, Sports Cabinet Secretary Salim Mvurya acknowledged that construction was progressing more slowly at the Kanduyi Stadium, but affirmed that the government had put in place measures to ensure the project is delivered within the set timeline.